Phase 1 - New Transmission Line to Pickle Lake

  • Potential construction start in December 2018
  • Potential construction completion in August 2020
  • Phase 1 cannot proceed without a plan for Phase 2

Phase 2 - Connection of 16 Remote First Nations communities

  • Potential construction start in December 2018
  • Remote community connections expected in 2021, with build out through 2023

Pikangikum Distribution Line Project

  • Pre-development phase completion September 2017
  • Construction start in October 2017
  • Construction completion in November 2018