Construction Progress
Phase 1 - New Transmission Line to Pickle Lake
·
Potential construction
start in Early 2019
·
Potential construction
completion in Late 2020
Phase 2 - Connection of 16 Remote First Nations communities
·
Potential construction
start in Late 2019
·
Remote community
connections expected in 2021, with build out through 2023
Pikangikum Distribution Line Project
·
Pre-development phase
completion September 2017
·
Construction start in October
2017
·
Construction completion in
November 2018